Assembly phased

A. BASIC PANEL INSTALLATION
B. INSTALLATION OF TEMINAL PANELS
C. FIXING OF THE MONOLITHIC SILL WITH ASSEMBLED CORNER
D. GROUT LINES SEALING

A. BASIC PANEL INSTALLATION

1.
Remove the panel from the wooden box

2.
Cut to size and/or make angles if necessary (see appropriate section)

3.
Place the panel at the wall, taking care to check the alignment of the vertical grout line

4.
Fix the base brackets and the upper brackets using the supplied rivets (pay attention to the correct positioning of the starting brackets, they must be fixed opposite to the upper ones)

5.
Place the supplied rivets on the bracket and tighten the bracket

6.
Place the panel at the wall, taking care to check the alignment of the vertical grout line

7.
Drill the holes for the dowel and fix the first external bracket using the special screw anchor (not included)




ZOOM

8.
Adjust the starting panel aligning both the plane and the depth (use shims on the back of the brackets to adjust any lead out of the masonry)

9.
Tighten the dowel

10.
Insert the kerf plate on the panel

11.
Fix the top panel on the kerf plate by inserting the tile spacers of the desired grout line (min 3 max 5 mm)




ZOOM

12.
Drill in correspondence of the top panel brackets

13.
Apply shims on the back of the brackets to adjust any lead out of the masonry

14.
Tighten the dowel